|
Corridor Sands -
an exciting opportunity for regional employment and contracts
Still in the planning stage of development, the US$500 million
Corridor Sands project contains immense deposits of titanium
dioxide minerals located near the town of Chibuto in the Gaze
province of southern Mozambique, 190 km north of Maputo.
The
deposits, located about 50 km inland from the Indian Ocean,
were discovered in late 1997 and represent the world's largest
known economic resource of titanium dioxide (TiO2) and
associated minerals. The size and scale of this mineral
deposit, accounting for a third of the world's known ilmenite
resources, is such that the eventual scale of operations could
rival the largest and most important producers of feedstocks
for the world titanium dioxide industry throughout the next
100 years. When developed, Corridor Sands will also be among
the lowest cost quartile producers.
"Estimates are that the Corridor
Sands ore body has a 100-year life, yet reserves have only
been delineated for the first 35 years," says project manager
for Corridor Sands, Brian Taylor.
About US$120 million has been
spent on the project to date, including the bankable
feasibility study, costing US$10 million. Up to US$87 million
will be paid by the Australian mining company, WMC Resources
Ltd, to acquire full project control from the South
African-based Southern Mining Corporation.
Mineral sands represents a new
commodity area for WMC, which is a company with total assets
approaching US$5 billion, underpinned by significant copper,
nickel, fertiliser and uranium oxide production. The Corridor
Sands project is WMC's first major venture into Africa.
Says Taylor: "The Mozambican
Government has been very co-operative and constructive. They
have been good to work with and have offered Corridor Sands
similar incentives offered to other large US$400 million plus
projects."
The
project is now 90% owned by WMC through its subsidiary
Corridor Sands Limitada, following the Industrial Development
Corporation of South Africa announcing its intention to
exercise its 10% option. The project is expected to involve an
initial investment of about US$500 million for the recovery of
400,000 tonnes of TiO2 slag. A total investment of US$800
million should ensure the project reaches an eventual
production level of one million tonnes of TiO2 slag.
Taylor says that since the
bankable feasibility study was completed in 2002, the project
team has been spending 2003 completing the estimate for the
export facilities, looking at optimising the design of the
operation and undertaking value engineering opportunities.
"In particular, we are currently
looking at the big ticket items and how we can improve their
overall cost effectiveness," he says.
One example of this is the
transport of product from the project site to the coast for
storage and shipping, using a road-train transport system.
This approach will typically use a three-trailer rig, with a
payload of over 100 tonnes per road train using a dedicated
black top road.
"We are completing the
environmental impact assessment work for this aspect of the
project and hope to integrate this approval within the
environmental license which has already been issued," Taylor
adds.
A power agreement for Corridor
Sands Ltd. is in place, but alternatives are being considered
and are still to be finalised. The EPCM contract for the
construction of phase one, which is planned to take 29 months
to complete, should commence in 2005. It is planned that the
smelter will be commissioned in 2007, with the first product
to be delivered to customers later that year.
Currently, the Corridor Sands
project is recruiting people for its team, which consists of
26 people located in Mozambique, South Africa and Australia.
At the peak of construction, there will be about 4,500
contractors on site. Phase one of the project will create 800
permanent jobs and an additional 500 semi-permanent contract
positions, and with the multiplier effect on further job
creation, it will indirectly lead to many new jobs in
Mozambique.
Infrastructure
According to the plan, silos
will be used to store the chloride and sulphate slags, while
the zircon and rutile will be bagged and stored under cover at
the storage area. The pig iron produced will be stored on
concrete pads. The storage facilities are expected to
accommodate about two months worth of production. The ships
loader will be capable of feeding between 1,000 and 1,500
tonnes per hour of product onto the vessels, and the jetty
facilities will allow for expansion as the project develops.
"We are still evaluating the
optimal stockpile-silo-shed design, and the best method for
loading the seagoing vessels," says Taylor.
The road, jetty and related
infrastructure should cost around US$80 million and will be
designed to accommodate Handimax (40,000 tonne) and possibly
Panamax (70,000 to 80,000 tonne) vessels.
During the first phase, Corridor
Sands will use around155 MW of power, increasing to 350 MW at
full capacity. The power infrastructure will cost about US$40
million and Taylor says this is an item close to the project's
critical path. The original plan was to purchase power from
Eskom, wheeled through to Maputo and then via a 200 km long
400 kV power line from Matola to the project site. However
alternative options are being evaluated to establish the most
cost effective package of securing reliable power at a
competitive price.
The Corridor
Sands deposit
The origin of the Corridor Sands
deposit lies in the history of the Limpopo river. Millions of
years ago the channel in which the Limpopo river now flows was
far larger, carrying all the waters of the present Zambezi,
Sashi and Kafui rivers as well as the flow of the Limpopo.
Structural uplift of the African continent associated with the
Rift Valley, has since redirected the Zambezi river from the
Limpopo valley - and in the process formed the Victoria Falls.
The mouth of this massive ancient Limpopo/Zambezi river system
was in the area of Chibuto where the river deposited its load
of heavy minerals, carried from far inland into the Indian
Ocean. The dual winnowing action of the longshore currents and
the sea winds resulted in the heavy minerals becoming
concentrated in huge beach sand dunes, which are now about 50
km inland.
Several separate ilmenite-bearing
sand deposits have been discovered within the project license
area. Work has focused on the largest of these, Deposit One,
which has been resolved into two higher grade zones called the
West Block and East Block. It is planned to mine the West
Block first, and this will supply more than the first 25 years
of plant feed at full production. However, enough drilling has
been completed over the East Block to establish indicated
resources there.
More than 1,100 aircore holes
have been drilled providing 65,000 metres of sample, of which
some 600 were drilled in the West Block with a "measured and
indicated resource" of 1,765 million tonnes containing 73
million tonnes of ilmenite at an estimated average ilmenite
grade of 4.14%. A total of 12 triple-tube diamond-tipped drill
holes covering 1,153 metres have also been drilled in the West
Block with good core recoveries. Down-hole geophysics and
trial pit testwork have indicated that true ilmenite grades in
the deposit are in excess of 15% higher than the values
indicated by aircore drilling. All of Deposit One
mineralisation extends from the surface with no overburden,
and thus no mining dilution.
Mining Corridor
Sands
The mining method proposed for
Corridor Sands is conventional truck and shovel mining. In the
early years, trucks are expected to have 100-tonne payloads,
but as the mine progresses other mining methods will be
evaluated, such as larger trucks and loading equipment, bucket
wheel excavators, trucking to a conveyor or pumping. Mine
planning will optimise the grade in the project's early years
starting in the high grade areas close to the site of the
proposed processing plant. Mining is expected to recover
ilmenite at a grade of 7% for the first five years and at a
grade of 5.4% for the next ten years.
The mine will be developed as an
advancing-face open pit mine, with the waste sand and unwanted
minerals deposited back into the pit behind the advancing mine
face, which will then be rehabilitated to international
standards. According to the plan, the mine pit design is being
optimised during the current engineering phase. The tailings
dam is also being reviewed with a view to achieving a more
cost effective design. As there will be no stripping ratio,
the pit size will be approximately 80 metres in length up to a
maximum depth of 160 metres, with a mining rate of 18 million
tonnes a year, operating 24 hours a day.

The processing
route
The testwork on the Corridor
Sands material has shown that it is suited to simple, proven
and cost-effective mineral separation and upgrading techniques
for the production of marketable products. The process will
involve a primary concentrator, a mineral separation plant,
and a roasting and smelting phase. A primary concentrator
plant will separate a heavy mineral concentrate from waste
sand and fines by simple water based gravity separation
methods, using spiral concentrators and cyclones. The
equipment specified for the primary concentrator is in use at
other operations within the mineral sands industry so the
technical risks are low.
The heavy mineral concentrate
produced by the primary concentrator plant will be a mixture
of various sand-sized particles, with ilmenite making up about
70% of the concentrate. The remainder of the concentrate will
be the by-product minerals, rutile, leucoxene and zircon, as
well as a small proportion of waste minerals. The mineral
separation plant will not alter the nature, size or chemistry
of the mineral particles, but will use the minerals various
physical properties to separate the individual products.
Ilmenite contained in the heavy
minerals concentrate will be extracted by a wet magnetic
separation process with the final stage of the mineral
separation plant being a dry mill that will separate the
rutile and zircon by using the differences in their surface
conductivity and magnetic susceptibility. The chromite in the
ilmenite is undesirable and this calls for a roasting stage,
which takes raw ilmenite from the mineral separation plant and
heats it to about 750°C. This process increases the magnetic
susceptibility of the ilmenite, which makes it easier to use
magnets to extract pure ilmenite low in chrome, but of high
enough quality to feed into the smelter. This roasting
operation will use the off-gas from the electric furnaces, and
no additional fuel will be required. Roasted ilmenite and high
quality anthracite will be fed to the furnaces through a
single hollow graphite electrode positioned in the centre of
each furnace.
Three furnaces, each rated at a
nominal 125,000 tonnes a year of slag production are to be
constructed for the first phase of the Corridor Sands project,
producing slag containing 85% TiO2. It is expected that
improvements in smelter design and operational improvements
will allow for the production of one million tonnes of slag a
year, when full production is reached, using only seven
furnaces. Smelter design and downstream processing are being
revisited to confirm and improve the design. The DC smelting
technology to be used is similar to that used by other
producers in South Africa "We have made a conscious effort to
seek out and engage proven technology with the Corridor Sands
project. This not only puts us a more certain footing, but
also represents less risk to shareholders," says Taylor.
The market for
Mineral Sands
Corridor Sands will be a
significant contributor to the titanium dioxide market,
initially providing 300,000 tonnes a year of titanium dioxide
units out of a market consuming 4.6 million tonnes a year, of
which South Africa currently supplies around 30%. A total of
54% of the world's known reserves of ilmenite are found in
southern Africa.
A project like Corridor Sands
and the products it is expected to produce are lifestyle
products and are linked to the world economy. It is expected
that the global economy will grow at close to 2.7% a year and
the increase in demand for titanium dioxide should grow in
line with this figure. It is anticipated that by the time the
Corridor Sands project expands to its full capacity of one
million tonnes a year, global demand will be about 5.2 million
tonnes a year. Even then, Corridor Sands will only provide
around 16% of the world supply, compared with Richards Bay
Minerals in South Africa and the Iluka operations in Western
Australia and USA, which supply well in excess 20% of the
world market each.
Since 2001, there has been an
oversupply of titanium dioxide feedstock and this is expected
to be back in balance again by 2007, assuming the world
economy follows the average growth trend. The annual increase
in demand for titanium dioxide is projected to be about
110,000 tonnes a year and Taylor says that Corridor Sands
wants to position itself to take the slack at the time the
market moves out of its state of surplus.
Of course, there are no
guarantees that the world markets will behave as expected, and
prior to the 2001 September 11 attack on the US and the SARS
virus in China and elsewhere, the window of opportunity for
the project had been 2005.
"We would not have fast tracked
the project, but the extra time gained has allowed us to be
very thorough, and evaluate many options. It suits us nicely,"
says Taylor.
Mining Review
Africa issue 5 2003
|