AIM-listed tin newcomer AfriTin Mining has completed the detailed mine design of its flagship Uis tin mine in Namibia.

Namibia – Following the completion of a mapping programme and construction of a 3D geological model, AfriTin has undertaken a detailed mine design for the V1 and V2 pegmatite bodies, previously identified as priority targets to supply feed to the new intermediary processing plant at its Uis tin mine.

The mine design includes an initial five-year mine production schedule to commence operations on the outcropping pegmatite bodies and existing excavations of the historical V1/V2 pits.

This internal mine plan supports an overburden stripping ratio of less than 1 (overburden-to-ore ratio) and a fast ramp-up profile using conventional open pit mining methods.

Material will be liberated through drilling and blasting; loading and hauling will be effected by combining excavators and articulated dump trucks. The run-of-mine feed to the plant for this phase of development is planned at 500 000 tpa with an anticipated annual production of 800 t of saleable tin concentrate (although at this stage, this rate is not guaranteed).

The target for the following phase remains 5 000 tpa of tin concentrate.

A plant location has been identified in close proximity to the V1/V2 pegmatite bodies. The site layout and project infrastructure is being finalised and earthworks and civil works construction are scheduled to commence during May 2018 with production on track for H2 2018.

"We are very pleased with the results of this early production phase mine design work that has recently been completed,” says AfriTin CEO Anthony Viljoen.

“Once operational we believe this will confirm the potential of the Uis project as a world-class tin mine with low operational risks,” he adds.

“Whilst we believe Uis has the resources to be a long-life operation, this phased approach, should provide a platform for sustainable early cash flows, says Viljoen, who adds that this approach should also de-risk the implementation of a larger scale mining and processing facility which in turn should allow AfriTin  to progress long term project financing options.