Orezone Gold Corporation
Orezone Gold Corporation exploration drill rig at Bombore gold project in Burkina Faso

Orezone Gold Corporation’s new feasibility study (FS) on its 90% owned Bomboré deposit is scheduled to be completed in Q2, 2018. The project will likely deliver strong economics thanks to a simplified flowsheet.

Burkina Faso – The FS, launched in January of this year, is being completed by a team of highly qualified engineering and environmental firms including Lycopodium Minerals Canada, AMC Consultants, Knight Piésold & Co., with the work being based on the 12 January 2017 mineral resource estimate.

All of these firms have extensive recent West African and Burkina Faso experience in both construction of new mines and the optimisation of existing operations. The FS is expected to be completed in late Q2, 2018.

Orezone has also contracted P&E Mining Consultants to complete an updated mineral resource estimate which will encompass all of the 2017 drill results and will also model the newly identified higher grade zones within the existing oxide pit shells using separate mineralisation domains. This updated mineral resource estimate should be completed in Q3, 2018.

Previous studies for the Orezone oxide mineral resource were based on combined heap leach (HL) and carbon in leach (CIL) processing and mining of all oxide material, including the harder more competent lower transition material at the bottom of the pits.

In mid-2017 Orezone commenced a detailed review of all work completed to that date to determine whether the prior 2015 Bomboré FS could be simplified. The company contracted Soutex, a specialised metallurgical consulting firm based out of Quebec City, to review all metallurgical test work, supervise the completion of certain additional metallurgical test work, and to assist in developing a revised flowsheet.

In conjunction with this the company visited a number of operating mines in West Africa that currently mine oxide material using contractors employing small 30 – 50 t haulage trucks in order to determine efficiencies, costs and suitability of adopting their practices to mine the Bomboré “free digging” oxides.

The results of the Soutex review concluded that the Bomboré flowsheet could be simplified through the elimination of the HL circuit, which should result in a simpler process operation. Under the simplified process, the focus would be on the “free dig” material only.

This would exclude the lower transition material which does require some drill and blast and crushing in order to be processed, but this only accounts for approximately 7% of the total mineral resource tonnes in the 2017 mineral resource estimate.

In preparing for the FS, Lycopodium worked closely with Soutex and reviewed the simplified flowsheet concept and concluded that this was the preferred option to examine in the FS from both from a capital and operating cost viewpoint. Site visits have also been undertaken by the FS consultants and all existing data reviewed.

Based on these visits, the data reviewed, the Soutex review, and the recently completed metallurgical test work, several key opportunities will now be examined in the FS:

  • Contract mining using low technology 30 t haulage units, currently used in several free dig operations in West Africa.
  • Simplified front-end processing through the process plant.
  • Construction of the Tailing Storage Facility (TSF) in phases over the mine life. Previous flowsheets and plant design for Bomboré necessitated the full construction of the TSF at the front-end thereby increasing the front-end capital cost.
  • A recently constructed 80-person camp at site as well as offices, kitchen, dining room, light vehicle repair shop, sample preparation laboratory and warehousing will reduce the requirement for further infrastructure for construction and operations.

“Our FS for the Bomboré project is very much on track,” says Patrick Downey, President & CEO. “The reviews and work completed over the past 10 months have lead us to a simplified process flowsheet. We expect that this simplification will confirm Bomboré as a compelling project.”

“Our consultants all have significant West African experience in design, construction and operations, which will bring relevant hands-on credibility to the FS. We are fully permitted and well financed to complete the FS and continue into detailed engineering in the second half of 2018. We also plan to commence the first stage of relocation in the second half of 2018 in order to be in a position to make a construction decision and to commence in 2019. We also expect to commence discussions on project financing for construction later in 2018. We are also very encouraged by the recent drilling results and we believe these, and ongoing drilling will continue to have a positive effect on the project.”