HomeGoldRoxgold on track to boost production in Burkina Faso by year-end

Roxgold on track to boost production in Burkina Faso by year-end

TSX-listed gold miner Roxgold’s mining decree for its Bagassi South project, currently in development, has been approved by the Burkina Faso Council of Ministers.

The Bagassi South mining decree is an extension of the existing 2013 mining convention currently in place at the 55 Zone and carries the same terms.

“Construction at Bagassi South has been progressing extremely well and we continue to be on track for delivery of first ore from our second mine expected in the fourth quarter,” comments John Dorward, Roxgold President and CEO.

“The process plant expansion is also tracking on schedule where we look forward to increasing Yaramoko’s gold production by approximately 40% to 160 000 oz in 2019.”

Development and construction at the Roxgold Bagassi South project, located 1.8 km south of the Yaramoko processing plant, has been advancing well with overall project completion now at approximately 55%.

The boxcut excavation is expected to be fully completed in early July. Portal ground support activities are nearing completion. The establishment of the collar is expected to be completed the first week of July, at which point the underground development will commence immediately thereafter on schedule.

Surface infrastructure elements are also tracking to schedule and budget. The haulage road, security building, fencing, settling pond, and TSF embankment raise construction have been completed and the remaining minor surface infrastructure items are expected to be completed by the end of June.

In addition, the expansion of a run-off water harvesting facility has also been completed allowing for increased water capacity at the site.

The process plant expansion project, which allows for an increase in throughput from 750 tpd to 1 100 tpd, also continued on schedule. The engineering design and procurement is now completed and fabrication is well advanced.

Civils at the plant are completed with Group 5 construction personnel ramping up numbers at site.

The overhead power line to Bagassi South is currently under construction and is expected to be completed in early August. The secondary crusher is being manufactured and is expected to be delivered to site in October as planned. Overall project completion is expected in the latter parts of the fourth quarter.