Anglo American Platinum, or Amplats, has made the pre-emptive decision to close the Anglo Converter Plant (ACP) Phase B unit again following a series of water leaks.

This is to ensure an ongoing safe operating environment, protect employees and protect the integrity of the plant and surrounding processing assets.

READ MORE: Amplats confident production guidance not affected by closure

“As indicated in our Q3 production report on 22 October, the ACP Phase B unit has been fragile and has unfortunately recently experienced a number of further instances of water leaks,” says Amplats CEO Natascha Viljoen.

Whilst the ACP management team has done extraordinary work to keep the unit operating safely over the past several months, we have taken this pre-emptive decision to now close the ACP Phase B unit to ensure we protect our employees, operating environment and the integrity of our assets.

“Whilst this early closure will result in a temporary build up in work-in-progress inventory, we continue to make good progress with the rebuild of the main ACP Phase A unit, which we expect to complete towards the end of this year,” says Viljoen.

Increased monitoring, controls and systems were implemented to continually assess the ACP Phase B unit and further water leaks were discovered. The ACP Phase B unit underwent a planned and measured shutdown. Whilst the ACP management team has been able to complete repairs to previous water leaks, after a comprehensive assessment, and with further water leaks discovered, the ACP Phase B unit now requires more extensive repair work. As a result, the ACP Phase B unit has been closed for a full rebuild in 2021.

As at 31 October 2020, Amplats has refined 2.4 Moz of PGMs. As production continues at approximately 94% of normal production levels, the closure of ACP Phase B unit until ACP Phase A unit is recommissioned will result in an increase in work-in-progress inventory, whose release will commence once the ACP is operational. The company has made significant progress with the Phase A unit and remains on track to commission it before the end of this year, ahead of the original schedule of Q2, 2021.

READ MORE: Amplats ramps up ACP plant to restart refined PGM production

As a result of the closure of the ACP Phase B unit, the company has lowered its refined production and sales guidance for 2020 to approximately 2.5 Moz PGMs (previously guided to be between 3.1 and 3.3 Moz of PGM).

There is no change to other guidance, including M&C production which remains at between 3.6 and 3.8 Moz of PGMs.

Amplats has contingency plans in place and will be engaging with customers to minimise any disruption to contractual obligations. As at 31 October 2020, the Amplats remains in a net cash position of approximately R28 billion (unaudited) and has R25 billion of committed facilities available.