DRA, the EPCM contractor for the 12 million tonne a year DMS project at Tati Nickel’s existing Phoenix mine 40 km north east of Francistown in Botswana began the project in August 2006. The US$151 million project is due to achieve full production in December 2008.

The project achieved its primary completion milestone of accepting its first material into the DMS system at the beginning of July 2008, on schedule, which is a significant achievement in the current project environment.

The new plant is sited within the existing concentrator complex and consists of a primary gyratory crusher, secondary and tertiary crushing and screening circuits, and associated materials handling systems, consisting of 42 conveyors. Over 950 tonnes of conveyor structural steel was designed and fabricated in India.

The crushed material, -25 mm in size, feeds the DMS section, built in four parallel modules, with a combined capacity of 1,600 tonnes per hour. By removal of the waste portion, a higher nickel grade product is fed into the existing milling circuit, thereby increasing the nickel concentrate volume processed through the existing concentrate plant.

Production at the Phoenix mine commenced in 1995 at 1.2 million tonnes a year using dry magnetic separation concentration due to lack of sufficient water. In 2000 a capital project was undertaken to increase tonnage and switch to the much more efficient conventional mill/flotation process. The 3.6 million tonne a year concentrator was commissioned in 2002. This included the construction of a 43 km water line from Shashe dam as well as an increased 20 MW power supply from Francistown. The concentrates are trucked 200 km to the smelter at Selibe Pikwe.

The gyratory primary crusher

The gyratory primary crusher
installed at Tati Nickel
by DRA
.

The Phoenix deposit consists of high grade lenses of massive nickel/copper sulphides surrounded by disseminated low grade ore. It requires very selective mining and blending to avoid wide fluctuations in the feed grade to the concentrator. The new DMS plant will also make a significant contribution to grade stability and will allow lower grades to be profitably mined.