Mali – Multi-listed gold company B2Gold Corp. has officially broken ground at its Fekola project in Mali.

The event was officiated by Robert Diarra, Chief of Staff of the Ministry of Mines, and well attended by national and regional government representatives as well as community leaders.

Initial construction activities at Fekola began in February 2015 led by core team members of the Otjikoto construction team. Early works construction activities that were completed included:

  • Construction of a new site access road (40 km from the tar road to site) complete with a bridge across a major waterway to allow for year round access;
  • Construction of an on-site airstrip designed to allow personnel to fly directly in and out of the site (materially complete but waiting for final regulatory approvals);
  • Construction of the camp pad and commencement of clearing within the mill footprint;
  • Crushing of aggregate to produce sand and gravel to be used in the concrete batch plant;
  • Construction of the concrete batch plant; and
  • Development of the on-site geotechnical laboratory to be used for compaction and concrete testing.

All of these activities allowed the project to move forward and prepare for work after the rainy season which runs from late June through September. The site has been receiving a steady stream of materials for mine construction which commenced in the fourth quarter of 2015. Activities that are currently scheduled include:

  • Commencing construction of the permanent camp;
  • Commencing excavation of the mill area; and,
  • Commencing clearing of the tailings basin.

Concurrently, with the activities on site, the B2Gold engineering team continues to work with Lycopodium Engineering in Australia to complete detailed design and procure long-lead items.

To date, many of the major mill packages have been identified and purchase orders have been issued. This includes SAG and ball mills, thickeners, cyclones, crusher, and tanks.

On June 11, 2015, the company announced robust results from the optimised feasibility study at Fekola. According to the feasibility study, the current average annual production for the first seven years is approximately 350 000 ozpa at an average operating cash cost of $418/oz and for the life of mine plan approximately 276 000 ozpa at an average operating cash cost of $552/oz.

The total pre-production capital costs are estimated to be $395 million plus $67 million of anticipated mine fleet and power generator costs which are expected to be lease financed.

Sunk costs related to early works (including access roads, construction aggregate stockpiling, airstrip construction, and land clearing) of approximately $38 million are not included in the total pre-production capital estimate. Based on current assumptions the Fekola mine is scheduled to commence production in late 2017.

B2Gold is projecting to produce between 500 000 and 540 000 oz of gold in 2015.

Top Project stories in Mali:

Hummingbird Resources completes earthworks at Yanfolila gold project

Mali’s Yanfolila gold project: Grade control & infill drilling start